Available hangar space is extremely limited at OSH with a waiting list of 50+ aircraft owners and pilots. These T-hangars will be the first airport-owned hangars built at OSH in more than 20 years.
Osh T Hangar Project 2023 Image 1

We are thrilled to announce that Wittman Regional Airport (OSH) will begin construction on twenty (20) brand new T-Hangar units in February 2023. Like many General Aviation (GA) airports, available hangar space is extremely limited at OSH with a waiting list of 50+ aircraft owners and pilots. These T-hangars will be the first airport-owned hangars built at OSH in more than 20 years. The two 10-unit buildings will be constructed on the east ramp directly south of the intersection of Taxiway J and Taxiway E. The project will also entail earthwork, taxi-lane construction, utility and stormwater features. Funding for the project is provided by a combination of County, State and Federal grant funding. Please refer to the attached renderings.

Each hangar unit will be sized to fit up to a light piston twin. They will have automatic bifold doors, concrete floors, and will be insulated and heated. One of the buildings will have a public restroom for use by all tenants and visitors in the east ramp area. As a part of the project site work, we will also be creating six shovel-ready hangar pad sites for up to 60'x60' privately-built hangars, with electric and gas connections nearby. Lots will be available for land lease in summer 2023.

Westwood Professional Services of Appleton, WI is the design / engineering firm on this project, Cardinal Construction of Fond du Lac, WI was selected to construct the buildings and R&R Wash Materials of Ripon, WI will be performing the civil site work. Demolition of the 50+ year old pavement and five structures that currently exist on the site will begin in February 2023, with completion of the project scheduled for late summer 2023.