Riga Airport Starts Operating New Rapid Exit Taxiway

Sept. 13, 2021
The rapid exit taxiway permits decreasing the distance of aircraft movement on the runway and taxiway.

Riga Airport on Sept. 9 started operating the second rapid exit taxiway that has been constructed with the support of the Cohesion Fund (CF).

The new rapid exit taxiway was first used by an aircraft of the national airline airBaltic arriving in Riga from Turku: https://ej.uz/rixrapidtaxiway

The rapid exit taxiway permits decreasing the distance of aircraft movement on the runway and taxiway. Thus, the airport will decrease the amount of fuel and time consumed during the land maneuvers, thereby also decreasing the amount of emitted pollutants – CO2, hydrocarbons and particles.

“The new rapid exit taxiway is another purposeful step of Riga Airport towards the development of sustainable airfield infrastructure. Being an airport that has undertaken to reach the zero-emission level by 2050, Riga Airport invests in the acceleration and efficiency of airfield processes thereby minimizing the amount of emitted pollutants. This is an investment in the future that cares for the environment and decreasing the climate changes,” stresses Laila Odiņa, chairperson of Riga Airport Board.

The construction works were performed by a tender-selected road construction company SIA Binders, and the total project costs amount to 2.6 million euros. The construction works required a specific work organization regime to avoid interruptions and other encumbrances to the airfield operation. Therefore, all technological processes of the construction works in the airfield territory occurred at night in-between flights. This period likewise covered the organization of material supply, construction machinery and equipment logistics.

It has already been reported that within the framework of the Cohesion Fund-funded project “Development of Safe and Environmentally Friendly Infrastructure at Riga International Airport," Riga Airport was carrying out the development of the airfield and airport territory infrastructure at a large scale. The airport taxiways have been equipped with centerline lights, thus taking the first step towards the introduction of the innovative “follow the greens” aircraft management system, and a helipad for EMS missions and search & rescue services, as well as military, and heads of states and other helicopters has been constructed.

Likewise, the CF support has been used to reconstruct the public access roads, modernize the rainwater sewerage and lighting infrastructure.

The support for airport modernization is planned within the framework of the planning document Priority Axis “Sustainable Transportation System” Specific Objective 6.1.2 “To Promote Security and Compliance with Environmental Requirements at Riga International Airport." Riga Airport concluded a contract with the Central Finance and Contracting Agency (CFCA) on Dec. 27, 2016 to receive the CF-funding for the implementation of the project. On July 3 2017, the airport received a positive decision of the European Commission (EC) concerning the state support notice for the project “Development of Secure and Environmentally Friendly Infrastructure at Riga International Airport” (project No. 6.1.2.0/16/I/001).

The total available financing for the project is EUR 23,049,010, of which the CF financing is EUR 10,774,241, and financing of Riga International Airport – at least EUR 11,564,245.