Colorado Airport Behind on Runway Reconstruction
The reconstruction project was scheduled to be completed by next Tuesday.
The delays will not add to the project's $32.2 million price, Faulkner said.
Workers still need to pour some concrete, finish electrical work for runway lighting and repave the runway shoulders, he said.
"It seems as though we're getting more and more done where less can go wrong," Faulkner said. "Every day, the window for the potential for things to go wrong gets smaller."
News stories provided by third parties are not edited by "Site Publication" staff. For suggestions and comments, please click the Contact link at the bottom of this page.
- « Previous Page
- 1
- 2
- Next Page »
Do you recommend this News?
We Recommend
-
News
New runway put on hold until March ; Date pushed back a 4th time to give ground time to thaw
Reconstruction of the main runway at the Colorado Springs Airport has been put on hold until March 1, airport officials said Tuesday. The $37.6 million project is scheduled to be completed...
-
News
Colorado Springs Launches Investigation of Runway
The inquiry comes after the city-owned airport learned this month of claims calling into question the work by the concrete contractor in 1991.
-
News
LAX Runway Will Be Closed During Major Construction
The project aims to improve airport security and prepare the airport for a new generation of jumbo jets.
-
News
LAX Runway Will Be Closed During Major Construction
The project aims to improve airport security and prepare the airport for a new generation of jumbo jets.