AIP Funding
AIP Funding
States prepare their airports for AIR-21 funding monies
By By Jordanna Smida, Associate Editor
October 2000
LONG BEACH, CA — While the state aviation officials gathered for the annual National Association of State Aviation Officials (NASAO) conference, officials spoke with AIRPORT BUSINESS on AIR-21 and the challenges of preparing for disseminating the funds to airports.
As the first stage of proposed funding
of AIR-21 nears completion, states across the country are beginning to
prepare their airports for what lies ahead.
Vice president of NASAO, Lori Leonard says
educating the airports, specifically the smaller general aviation airports,
should be the states’ priority.
"I think the most important thing is
to educate the sponsor in what it means to take a grant... It’s important
for them to look at their airport plan, the needs that are there, what
their facilities are at this point and what the forecasts are for demand
of the airport, what needs they want to meet, and how they want to do
that. It has to be agreed upon by everybody so as they start planning
to spend the funds that they have a positive plan in place (that) the
state, the sponsor, and FAA can all agree to."
The state of Mississippi has 66 general
aviation airports eligible for funds. In 1998 the state completed its
airport system plan, which according to state director Elton Jay, most
of the airports are using as a guide for what’s needed and what’s
eligible. Like Jay, many other airports are holding regional meetings
with FAA officials and the airports to educate them on the grant and funding
procedures.
"A problem is that some of these small
airports haven’t had a grant in five or ten years and the administration
has changed, engineers changed, and they don’t have anybody locally
that is familiar with the program," he says.
Many other states are encountering similar
obstacles, and as a result are taking on a liaison role between their
airports and the FAA.
In 1995, Florida, which has 80 publicly
owned general aviation airports and spends over $100 million a year on
its airports, developed a partnership database of needs with the airports,
the FAA, and the state. The airport needs are placed in the database and
reviewed by the state and the FAA to project what can be funded, explains
William Ashbaker, state aviation manager for Florida. Though the database
has created a solid working relationship between the three groups, Ashbaker
says there is still a need for some education on grant applications.
UTILIZING THE FUNDS
Though additional Airport Improvement Program
(AIP) funds will ease some airport projects, many states are concerned
about how they will match and utilize the funds.
Jay, whose state intends to take this opportunity
to bring its airports up to standard, says, "The burden will be in
the decisionmaking. We have to determine which airports will have to roll
their money over to 2002 or 2003 to fund a project. We have a good handle
on 2001, and with 2002 and 2003, what will really impact that is how much
state apportionmate money we get in addition to this $150,000 per airport.
Not until we know that will we know which one we can actually fund in
2002."
One of the biggest challenges the airports
face, Ashbaker says, is coming up with the local match. Florida provides
80 percent of the funding and the small airports are required to fund
the re-maining 20 per-cent or get FAA dollars, he says.
Florida is working closely with the FAA
to plan airport needs and both are in the pro-cess of deter-ming how the
funds will be disseminated. "Originally we’d talked with them
about having them pass the money to us and we would include it in our
grants for the small airports," Ashbaker says.
Matching AIP grants is also a concern for
California, which matches 5 percent of the funding for its 255 airports,
explains Marlin Beckworth, California program manager. "I have a
certain dollar amount set aside for AIP matching purposes. With the increase
in funding that may or may not be sufficient to match the grants that
come in to the state. We’re going to have to take a hard look at
that and ensure that we’re not a bottleneck in terms of our AIP matching
process," he says.
Beckworth also says his state isn’t
comfortable with the allocation formula, noting some airports will be
left out. He’s also concerned, like many other states, that some
airports don’t have the administrative capability to handle the funding.
His goal is to as-sess the funding plans for non-NPIAS (National Plan
of Integrated Airport Sys-tems) airports and look at solutions like swapping
funds between the state and federal level in order to compensate for some
of those holes in the process.
One of the challenges block-grant state
Wisconsin faces, according to airport programs section chief, Dan Finklemeyer,
is the airports that have already completed projects and don’t have
another on the books. "We’re meeting with those airports to
lay out what monies we think will be available," he says. Currently,
37 airports in the state have the potential to receive entitlements.
According to Leonard, some states are looking
to get groups together and have the state manage the grant. She says some
states are discussing options such as combining pavement maintenance projects.
The state would contract, advertise, and bid the project with the airports
getting the projects they need completed, she explains. "I think
the other thing the states can consider is doing projects where they can
find a cost-effective way of getting the projects done at a variety of
airports across the state."
- « Previous Page
- 1
- 2
- Next Page »
Do you recommend this Article?
We Recommend
-
Article
Pavement Maintenance
Pavement Maintenance By John Boyce, Contributing Editor January/ February 2001 Tapping AIP dollars to keep up runways, ramps, taxiways Pilot program leads to previously...
-
Article
Disseminatgin $10 Billion
Disseminating $10 billion Senior FAA airport officials talk about the task before them By John F. Infanger, Editorial Director June 2000 BALTIMORE — When President Clinton...
-
Article
States Tackle Security, Funding
-
Press Release
LaHood Announces $1 Million Grant for Greenwood Municipal Airport
The grant will provide for the replacement of runway pavement and extend the runway to meet the needs of aircraft using the airport. The project will begin this fall.